Write a factory acceptance test before shipment. Use your own alloy, flask and part families to check a CYLANCO CXM-C18 or CXM-C20 under agreed production conditions.
Agree on acceptance before ordering
Start with the ordered machine and revision, its matched flask and accessories, and three sample families: a routine part, a fine-detail part and a repeat reject from the current process. Supply the agreed drawings and defect photos. Define how each batch will be scored for dimensions, incomplete fill and visible surface defects. Confirm which internal checks require a sectioned sample or an outside laboratory.
Capture a run another operator could repeat
Record the alloy lot, tree layout, flask size, mould preparation, transfer timing and machine recipe. Log test batches in sequence, keeping start-up and interrupted cycles identifiable. Where vibration is part of the quoted CXM-C20 configuration, record the stage and setting used. For a remote witness, agree in advance on what needs live camera coverage and retain the machine log and marked samples.
Link the factory test to installation
The final test sheet should show what passed, any exceptions, who owns the corrections and the retest method. Once the machine reaches the buyer's site, confirm the agreed utilities and repeat representative parts with the local team. Keep the factory and site results together so any change in setup or process can be traced.